Applied Digital Reaches Ready for Service on First 25 MW at Polaris Forge 2
Applied Digital completed base-build commissioning for the first 75 MW of the initial 150 MW building at Polaris Forge 2 and achieved Ready for Service for its first 25 MW data hall on schedule. The remaining 50 MW in the phase can now advance through fit-out and customer delivery. The building is fully leased as part of the customer's 200 MW long-term lease, contributing to a portfolio of more than $41 billion in contracted base-term lease revenue.
Key takeaways
Base-build commissioning was completed for the first 75 MW of the initial 150 MW building at Polaris Forge 2 in Harwood, North Dakota.
The first 25 MW data hall achieved Ready for Service on schedule.
The remaining 50 MW in the phase can advance through fit-out and customer delivery.
Each 150 MW building is commissioned in two 75 MW phases, with three 25 MW data halls tested and commissioned together during each phase.
The building is fully leased as part of the customer's 200 MW long-term lease at Polaris Forge 2.
Applied Digital reported more than $41 billion in contracted base-term lease revenue across its portfolio.
The milestone followed delivery of 250 MW of operational critical IT load at Polaris Forge 1 in Ellendale, North Dakota.
Key metrics
Primary source
TickerStar generated this brief from an official company, investor-relations, earnings-call, or regulatory source. Review the primary material before making an investment decision.
Open Investor relationsFollow APLD in real time
Get material earnings, filing, IR, and earnings-call alerts by email.