FRMI 10-Q filed 2026-11-12 | Key takeaways
FRMI filed its 10-Q; the most relevant disclosure change is expanded Tenant agreements and lease status: The TensorWave lease was terminated on November 10, 2026 after the October 31 closing date passed without an extension, with no effect on the Q3 financial statements. On November 10, Fermi entered a nonbinding LOI for approximately 600 MW with an investment-gr.
Key takeaways
Tenant agreements: The TensorWave lease was terminated on November 10, 2026, while a new nonbinding LOI for approximately 600 MW remained subject to definitive documentation.
Liquidity: Cash, cash equivalents and restricted cash increased to $315.5 million from $91.7 million at June 30, but management continued to identify a need for plans to address substantial doubt about going concern.
Debt covenant: The October 9 Turbine Warehouse amendment set minimum quarterly principal payments at 5% and waived specified potential defaults, but the requirement for committed financing for at least 400 MW by February 10, 2027 remains.
Nuclear schedule: The NRC published a draft environmental impact statement for four AP1000 units, while the expected commissioning schedule moved to 2034, 2035, 2036 and 2037, respectively.
Legal matters: The Firebird case was dismissed with prejudice without payment by Fermi, while Class B Unit Reclamation litigation was ordered to arbitration and Bayonne claims of at least $8.5 million remained pending.
TTU lease condition: Fermi must receive a notice to proceed by December 31, 2026, with a Phase 1 tenant lease for at least 200 MW among the conditions, and had no definitive tenant lease as of the filing date.
Operating results: Fermi remained pre-revenue and reported $142.2 million of quarterly general and administrative expense and a $141.6 million net loss.
Key metrics
Disclosure changes
- Tenant agreements and lease status
The TensorWave lease was terminated on November 10, 2026 after the October 31 closing date passed without an extension, with no effect on the Q3 financial statements. On November 10, Fermi entered a nonbinding LOI for approximately 600 MW with an investment-grade hyperscaler, accompanied by $200 million prepayment and $15 million early construction and site development agreements that also had no Q3 financial-statement effect.
The named tenant agreement was terminated, and the replacement hyperscaler arrangement remained nonbinding; the filing states that Fermi had no definitive tenant lease as of the filing date. - Liquidity and going concern
Fermi held $286.327 million of cash and $29.190 million of restricted cash at September 30, 2026, compared with $62.536 million and $29.195 million at June 30. The company continued to state that these resources were insufficient for projected one-year obligations without management plans, but concluded that its plans were probable to alleviate substantial doubt and prepared the statements on a going-concern basis.
The cash increase came with substantial capital expenditure and debt obligations, while the going-concern conclusion remained dependent on financing availability and capital-expenditure sequencing. - Debt, net
Gross debt increased to $999.948 million and net debt to $958.353 million, including $431.25 million of convertible notes, $444.862 million under the Turbine Warehouse facility, $91.535 million of high-voltage financing and $32.301 million under Turbine Warehouse II. The Macquarie loan had been repaid, and the Yorkville promissory-note commitment had fallen to zero without any draw.
Net debt increased by $438.262 million from June 30, 2026, while the filing added collateral, repayment and project-financing terms. - Turbine Warehouse Equipment Financing
The October 9 amendment set minimum quarterly principal payments at 5%, eliminated the condition under which payments would increase and equipment could be marketed absent a 400 MW lease or offtake agreement, permitted relocation and storage of financed equipment, and waived specified potential defaults. Fermi paid $25 million of amendment fees, MUFG assigned the loans and commitments to a lender syndicate, and the separate requirement for committed financing for at least 400 MW by February 10, 2027 remained.
The amendment reduced the near-term amortization and equipment-marketing trigger, but added a $25 million fee and left the 400 MW project-financing requirement in force. - Nuclear Program Update
Hyundai completed a front-end engineering design study in July 2026, and the NRC published a draft environmental impact statement for four proposed AP1000 units on October 9, with comments due through November 23. The expected commissioning schedule is now 2034, 2035, 2036 and 2037, reflecting an approximately one-year delay for the first unit.
The filing adds regulatory-review milestones and a revised schedule for the first of four planned nuclear units. - Hillcore Framework Agreement
The current filing expands the Hillcore framework to an initial approximately 360 MW block within a planned facility of up to approximately 2.6 GW, describes take-or-pay offtake obligations covering at least 50% of aggregate tenant power requirements, and states that definitive-document negotiations had been extended to December 18, 2026.
The BOOT arrangement could reduce direct generation capital expenditures, but definitive documentation had not been executed and the filing stated that consummation was not assured.
Primary source